Trinidad Hummingbird AI Agreement: What the $5 Billion Data Centre Deal Really Means
If you don’t want to read the whole guide or have difficulty reading, you can listen to this guide instead.
On July 11, 2026, Trinidad and Tobago signed three agreements with American companies, and the one that drew the most attention was the trinidad hummingbird ai agreement. It covers a proposed 150-megawatt AI data centre, with room to grow to 500 megawatts, and it sits inside a package officials value at more than 5 billion dollars.
At AI Holic, we read the government statement, news reports, and regional governance analysis to show what was actually signed and what is still only a plan. This guide explains the deal in plain terms, who the companies are, what the money figure means, and the two questions about power and water that will decide whether anything gets built.
You will learn what each agreement covers, why the Hummingbird company drew questions, how the power and water numbers stack up, and what must happen before anything is built.
What the Trinidad Hummingbird AI Agreement Actually Is
The trinidad hummingbird ai agreement is a memorandum of understanding, or MOU, between the government of Trinidad and Tobago and Hummingbird AI Holdings LLC, a company based in Florida. It was signed on July 11, 2026, by Foreign and CARICOM Affairs Minister Sean Sobers, acting on behalf of Prime Minister Kamla Persad-Bissessar. The signing was announced at a United States Embassy reception marking America’s 250th independence anniversary.
A memorandum of understanding is a formal statement that two sides intend to work together. It is often used where the parties do not want to create a binding legal commitment yet. That point matters more than any other in this story, because every figure attached to this deal carries the same qualifier.
The Hummingbird MOU sets out a framework for “preliminary cooperation, due diligence and coordination” around a proposed 150-megawatt AI infrastructure and data centre facility. The facility could expand to 500 megawatts over time. Initial commercial operation is targeted for the first quarter of 2028, but only if due diligence succeeds and the project moves ahead.
Government officials described the three July 11 agreements as the first of their kind between major American technology and services firms and any Caribbean nation. The United States government played a facilitative role in bringing the parties together. That first-of-its-kind label is part of why the deal drew attention far beyond Trinidad and Tobago.
Nothing in the MOU commits either side to build. No construction approvals have been issued, no environmental permits have been granted, and no final investment commitment exists. The government has said plainly that all three initiatives remain at the framework and due diligence stage.
The Three Deals at a Glance
The Hummingbird agreement was one of three MOUs signed on the same day. The other two matter to the story, because the headline figures cover all three together. Here is the full package in one place.
| Agreement | Partner | What it covers | Size and timing |
|---|---|---|---|
| Data centre framework | Ernst and Young LLP (New York) | Framework to develop a large data centre using EY’s Energy to Intelligence platform, with third-party developers on construction | 300 megawatts |
| AI infrastructure | Hummingbird AI Holdings LLC (Florida) | Proposed AI infrastructure and data centre facility, with due diligence first | 150 megawatts, expandable to 500 megawatts, targeted for early 2028 |
| Steel plant restart | Pinnacle Steel and Vanadium Corporation with PLIPDECO | Refurbish and recommission the Point Lisas iron and steel plant, with vanadium supply ambitions for American aerospace and defence buyers | No capacity figure stated |
Taken together, the two data centre projects would start at 450 megawatts and could reach 800 megawatts at full build. That combined figure is the one most reports quote. Keep the split in mind, because the two facilities are separate projects with separate partners and separate risks.
Who Is Hummingbird AI Holdings?
Hummingbird AI Holdings LLC is based in Florida, and at the time the MOU was signed it had little to no public footprint. Data Center Dynamics, a trade publication that covers the industry, described the company that way in its reporting. That thin public record is the main reason the deal drew hard questions from the start.
The company is led by managing member Marc-Kwesi Farrel. According to a press release from the United National Congress, the party of Prime Minister Persad-Bissessar, Farrel is a non-executive director at Massy Holdings, a Trinidad and Tobago conglomerate with interests in retail, energy, and cars. He is also the founder of the Caribbean rum brand Ten To One Rum, a former vice president at Starbucks, and previously worked at Bain.
What is not clear from the public record is whether Farrel or his company has experience building data centres. Data Center Dynamics reported that it is unclear whether he has experience with the data centre industry.
The company later acknowledged that it was formed specifically to pursue the Trinidad and Tobago opportunity, according to a column in the Trinidad Express. That fact alone proves nothing about the project, but it explains why critics asked for more detail.
The fair way to read this is simple. A new company with no track record in hyperscale infrastructure is not proof of a bad deal, and a well-known name is not proof of a good one. The due diligence period exists to answer exactly these questions, and the public deserves to see the answers before construction starts.

What the $5 Billion Figure Really Means
Government officials put the combined potential investment from the three agreements at more than 5 billion US dollars. They also put the projected job count above 5,000 skilled and semi-skilled positions. Both numbers come from the government, and both describe potential, not money already spent or jobs already created.
The word potential does real work here. An MOU is a framework for study and negotiation, not a signed construction contract.
The trinidad hummingbird ai agreement can change shape during due diligence, shrink, or fail its review entirely. Until a final agreement is signed and permits are issued, the 5 billion dollar figure is a projection of what could happen, not a promise of what will.
The jobs figure needs the same care. More than 5,000 jobs is the projection if all three projects go ahead at full size.
Construction jobs, permanent operating jobs, and indirect jobs are different things, and the government statement did not break the figure down. Readers should ask for that breakdown when the final agreements appear.
One later fact is worth noting separately. In October 2026, budget documents showed the government had spent 15 million dollars in fiscal 2026 through the Ministry of Public Administration and Artificial Intelligence on a Tier 4 data centre.
That is government spending on its own national data centre project, not money from the EY or Hummingbird agreements. The two should not be mixed up.
The same budget reporting found no record of environmental clearance applications for either MOU facility in the Environmental Management Authority’s public register. The Prime Minister also said the companies had not yet submitted their facility designs for approval, and that negotiations with state enterprises were still outstanding. Those are normal early-stage facts, and they show how far the projects still have to travel.
Power and Water: The Two Big Questions
Every serious question about this deal comes back to two resources: electricity and water. Data centres use a lot of both, and Trinidad and Tobago has limits on both. The numbers below explain why the debate has been so heated.
On power, the numbers are stark. The trinidad hummingbird ai agreement alone covers 150 megawatts at first and 500 at full expansion, while the EY deal adds 300 more. The country’s total generation capacity is about 2.4 gigawatts, according to the Ministry of Energy and Energy Industries.
The two data centre projects at full build would need up to 800 megawatts, or about one-third of the country’s existing capacity. Opposition members of parliament have gone further, claiming the projects could push national demand to 2,050 megawatts and pass current capacity. That is an opposition claim, not a confirmed figure, and it should be read as part of the political debate rather than as a technical fact.
Even the uncontested numbers show a real strain, and the grid has failed before. An island-wide blackout in August 2022 lasted more than 12 hours and shut down water treatment plants and booster stations across the country.
On water, the country has dealt with shortages in the past year because of problems with pipe infrastructure. Critics asked the direct question: can a small tropical country that already struggles to keep water flowing support facilities that need huge amounts of cooling water? The government has answered that purpose-built ponds will serve the projects in the short term, with desalination plants to follow, and that residential and commercial water supplies will not be affected.
Public Utilities Minister Barry Padarath confirmed the facilities are expected to sit inside the Debe Special Economic Zone, off the M2 Ring Road at Golconda in south Trinidad. Golconda is a small community of about 1,900 people according to the 2011 census, in the Penal-Debe region. Other sites were floated in public discussion before Debe was chosen, including Point Lisas, Picton, Usine Ste Madeleine, Brechin Castle, and Beetham.
The public response was fast. Conservation researcher Syam Nath launched a petition on July 12 asking the government to pause approvals until independent environmental, water, and infrastructure assessments are published and opened to public comment.
When checked on July 13, the petition showed 11,459 verified signatures. That number kept changing as more people signed.

The Governance Clock: A Rulebook That Arrived Second
The most interesting part of this story is not the money. It is the calendar. Three important events happened in Trinidad and Tobago within seventeen days in July 2026, and the order they happened in tells you a lot about how Caribbean AI policy is being made.
On July 7, CARICOM’s Council for Trade and Economic Development on Information and Communication Technologies endorsed the UNESCO Caribbean AI Policy Roadmap. CARICOM is the political and economic union of 15 Caribbean member states, and Trinidad and Tobago was one of its founding members in 1973. The roadmap was built from more than 1,000 stakeholder consultations across the region since 2024, and it rests on UNESCO’s Recommendation on the Ethics of AI.
On July 11, the government signed the three MOUs. Twelve days later, on July 23 and 24, the Caribbean AI Task Force handed over its Final Report at the first Caribbean AI Forum, held at the University of the West Indies St Augustine campus, only a few kilometres from where the data centre deals were signed.
The task force was convened by the Caribbean Telecommunications Union in July 2025 and chaired by Dr Craig Ramlal of UWI St Augustine. More than 35 experts from Caribbean governments, regional institutions, academia, civil society, and the private sector took part. Its Final Report sets out five priority areas: regional AI governance, data sovereignty and digital infrastructure, innovation and industry development, human capacity and AI literacy, and sustained multi-stakeholder engagement.
Read in order, the sequence is striking. The capital moved first and the rulebook arrived second, in the same country, within the same month. The Caribbean AI Association, which analysed the sequence, put the question plainly: the due diligence period ahead will show whether the task force’s priorities get folded into the contracts before they are finalised, or whether the report becomes a document negotiators consult after the fact.
There is a fair case on both sides. Eighteen months of due diligence is exactly the window in which a national AI governance framework could be written and applied to a deal already on the table.
That may be faster than legislating first and attracting investment second. The other case is that once investment and jobs figures are public and popular, the harder questions about data sovereignty, water, and grid capacity get settled on the investor’s clock rather than the country’s.
Our guide to unified AI governance architecture explains the kind of framework that could answer those questions, with clear rules for who decides what, who owns the data, and who checks compliance. The Trinidad deal is now the live test of whether such a framework can catch a deal already in motion.
What Happens Next
The trinidad hummingbird ai agreement now enters its due diligence phase, which runs to the first quarter of 2028 on Hummingbird’s own timeline. That is about eighteen months from the signing. Here is what has to happen in that window before anything is built.
- Technical, commercial, and regulatory due diligence on both data centre projects, including the EY facility and the Hummingbird facility.
- Facility designs submitted by both companies for government approval. As of October 2026, neither company had submitted designs.
- Environmental clearance applications filed with the Environmental Management Authority. As of October 2026, none had been filed for either facility.
- Negotiations with state enterprises completed, including land, power, and water arrangements.
- Feasibility studies and technical analyses of the kind Minister Dominic Smith described in his public comments after the signing.
- A final investment decision by each company, turning a non-binding framework into a real contract.
AI news moves fast, and this story will change as each of those steps lands. Our roundup of AI writing tools updates from April 2026 shows how quickly new AI products reach the public while big infrastructure deals are still working through due diligence. The same pace applies here: check the government statements and the Environmental Management Authority register, not just the headlines, when you want the current state of play.
What This Means for the Caribbean
The trinidad hummingbird ai agreement gives Trinidad and Tobago a first-mover position it did not hold before July. It is the first Caribbean nation to sign data centre agreements of this kind with American firms, and other CARICOM governments are watching closely. The Caribbean AI Association has argued that investors will approach other governments with similar offers within the next eighteen months, and that each government should have its own governance position ready before that call comes.
The deal also tests a real tension in the region. Caribbean countries want the investment, the jobs, and the digital infrastructure.
They also want control over their own data, their own power grids, and their own water. A 500-megawatt AI facility processes vast amounts of data, and the questions about who owns that data and who can access it have not been answered in public yet.
Governments are not the only ones moving fast on AI. In the United States, State Farm moved to mandate AI usage and cut agent pay at the same time, showing how quickly AI decisions now land in boardrooms as well as in cabinet rooms. The pattern is the same in both cases: the technology moves first, and the rules catch up after.
For Trinidad and Tobago, the stakes are concrete. The country currently has five data centres, four in Port of Spain and one in Princes Town, and none of them is an AI facility.
Reporting in the Trinidad Express noted that the country currently has no sovereign-grade data centre infrastructure at all. If the Hummingbird and EY projects are built, that changes. If they fail due diligence, the country will have spent eighteen months learning what its grid, its water system, and its governance rules can actually support.
Frequently Asked Questions
What did Trinidad and Tobago actually sign?
On July 11, 2026, the government signed three non-binding memoranda of understanding with American companies. One covers a 300-megawatt data centre with Ernst and Young, one covers a 150-megawatt AI data centre with Hummingbird AI Holdings, and one covers restarting the Point Lisas steel plant. None of the three is a construction contract.
Is the Hummingbird data centre guaranteed to be built?
No. The trinidad hummingbird ai agreement is a framework for due diligence, not a promise to build.
The facility is targeted for early 2028 only if the project passes technical, commercial, and regulatory review. It can still change shape, shrink, or stop entirely.
Where would the data centres be built?
Government ministers have said the facilities are expected to sit inside the Debe Special Economic Zone, off the M2 Ring Road at Golconda in south Trinidad. The site was confirmed after several other locations, including Point Lisas and Brechin Castle, were discussed in public.
Why are people worried about power and water?
At full build, the trinidad hummingbird ai agreement and the EY deal together would need up to 800 megawatts, about one-third of the country’s 2.4 gigawatt generation capacity. The country has also had water shortages from pipe infrastructure problems. The government says ponds and later desalination will protect household water supplies, but critics want independent assessments published first.
What is the Caribbean AI Task Force report?
It is the Final Report of the Caribbean AI Task Force, launched on July 23 and 24, 2026, at the first Caribbean AI Forum in Trinidad. It sets out five priority areas, including regional AI governance and data sovereignty, and it is the closest thing the region has to a shared rulebook for deals like this one.
Conclusion
The trinidad hummingbird ai agreement is a real opportunity and an open question at the same time. Watch the due diligence, the environmental filings, and the facility designs, because those documents will show whether the 5 billion dollar promise becomes a building or stays a headline.